The construction of the last stage of the Pri Mýte project has already reached the halfway point in terms of the final height of the building.
The implementation of reinforced concrete structures is currently underway on the fifth floor, while we are also working on bricklaying walls on the first floors. We are finalizing the entrance to the garage, distribution, and sewage systems. At the end of the month, we are planning to install window frames on the second and third floor.
One of the major advantages of the last stage of Pri Mýte is its location and excellent accessibility to the city center, which is just a few minutes away by car or public transport. In case you fancy a little stroll, you can get to the center in 25 minutes.