During the upcoming two months, we are going to focus on facade insulation of individual houses and wall plastering inside the apartments. We will also continue with window and roof installation as well as floor screeding.
This week we even began working on road infrastructure.
Upon its completion, the second phase of Bory Bývanie project will be surrounded by green park with a lake, recreation areas, enclosed playgrounds and a multifunctional sports ground